How long does the removal and installation usually take?
Typically 4-5 hours for a single oil tank installation. The installation of two tanks can be a full day job. Jobs that require bollards in a garage oil tank installation will be a full day. Jobs that require the installation of a cement pad (inside or out) will be a 2 phase job. The cure time for a new cement pads is 72 hours. Depending upon the location of the tank installation a temp tank may also be needed. Tanks installed with a new cement pad in an existing location require a temp tank. Tanks installed with a new cement pad in a new location do not require a temp tank. In cases where the tank is installed in a new location, the crew will install the cement pad on the first visit, then return after 72 hours (or whenever is convenient for the client) and install the new tank.